Abeeólica sues to halt Brazil battery auctions over cost charge

Abeeólica asks Brazil's Federal Court to suspend the December 2 and 4 battery storage auctions and challenges a charge split only among power generators.

The Brazilian Wind Energy and New Technologies Association (Abeeólica) took to the Federal Court, on Monday, November 16, 2026, the capacity reserve auctions for contracting battery energy storage systems, scheduled for December 2 and 4. Through a public civil action filed against the Federal Government and the National Electric Energy Agency (Aneel), the association seeks emergency injunctive relief so that the auctions do not take place under current conditions. The central argument is that the law shifted payment for this contracting exclusively to generators, and that the way of dividing this cost among them has not yet been defined by the regulator.

What the lawsuit challenges

The case is before the 17th Federal Civil Court of the Federal District. The main target is paragraph 6 of article 3-A of Law 10,848/2004, a provision added by Law 15,269/2025. This passage establishes that the costs of contracting batteries will be shared only among generation agents, according to rules to be set by Aneel.

For Abeeólica, the provision departs from the logic that guides capacity reserve in the country. In this model, contracted capacity works as insurance for the power system, and the cost is usually distributed among end users of the National Interconnected System (SIN). The association argues that those who benefit from the additional reliability are consumers, not just those who generate power. The filing also claims that treating funding differently depending on the contracted technology violates constitutional principles such as equality, free competition, legality and legal certainty, in addition to affecting investments made under previous rules, especially in wind and solar farms.

The action was filed by the law firm Justen, Pereira, Oliveira & Talamini. The association states that it does not seek to block the contracting of storage, but rather to prevent the auctions from taking place before the legal and regulatory disputes are resolved. The request preserves the possibility of the auctions taking place after the issues raised are corrected.

Cost allocation without a final rule

The second pillar of the action is regulatory. Aneel opened public consultation 37/2026 to discuss how the charge would be distributed among generators. The consultation ended on November 6, but the regulation has not yet been finalized. The proposal under review assigns participation factors ranging from 25% to 100%, depending on the degree of flexibility of each source. In Abeeólica's view, this could lead some generators to pay up to four times more than others, without the law having set criteria for this distinction.

Without a finalized methodology, according to the association, agents cannot calculate the economic impact of contracts that will last 15 years, with supply expected to start in August 2028. The petition also questions the idea that the cost would be fully passed on to consumers. Regulated market contracts may contain charge-recovery mechanisms, but this protection would not necessarily be guaranteed in free market contracts, which would leave part of the bill with the generators themselves.

The legislative front

The issue is also moving forward in Congress. On October 27, Aneel concluded that any change to the law assigning funding to generators will require a new assessment by the agency of the effects on contracts. In parallel, bill 3,716/2026, which changes the cost allocation for this contracting, is under consideration, and federal deputy Arnaldo Jardim (Cidadania-SP) discussed the subject in a conversation with MegaWhat. In other words, the funding rule may be changed through the judicial, regulatory or legislative route, and each path has its own timeline.

What this means for the Northeast

The Northeast concentrates a large share of the connection potential for batteries and, at the same time, a large base of wind and solar generators that would be called upon to pay the charge. A survey by ENLACE of 86 substations in the region eligible for LRCAP 2026 shows that 27 substations in Bahia and 24 in Ceará appear in the ONS technical note with available connection margin, in addition to all those analyzed in Piauí. This means that storage projects already structured around these points depend directly on the December schedule being maintained.

There is also a cross effect: many of the agents developing batteries in the region also operate renewable plants. For these groups, the same decision may represent new revenue on one side and an additional charge on the other, which makes the definition of the cost allocation especially sensitive for those operating in Ceará, Piauí and Bahia.

Our take

In our assessment, the action does not question the need for storage in the system, and this is relevant. What is in dispute is who pays and under what criteria. Even so, we see that litigation just weeks before the auction adds a layer of uncertainty to a market that is taking its first steps in the country, and the perception of risk may influence prices and bidding strategies.

The most uncertain point is the combination of three parallel fronts: the decision on the emergency injunction at the 17th Federal Court, the completion of the regulation following public consultation 37/2026, and the progress of bill PL 3,716/2026. If the auctions take place before the cost allocation methodology is published, 15-year contracts may be born with an open cost variable for part of the sector. If they are postponed, the supply start planned for August 2028 is likely to become tighter.

In the coming weeks, we will follow the Court's response to the injunction request, any statements by the Federal Government and Aneel in the case, the publication of the final cost allocation rule and any move by Congress on the bill. The dates of December 2 and 4 are the reference milestone.

What changes in practice for the BESS chain

  • Developers: keep qualification documents ready, but plan scenarios with and without postponement, including the impact on the schedule through August 2028.
  • EPCs: review proposal deadlines and quote validity, considering that contract signing may be pushed back.
  • Manufacturers and suppliers: follow the court decision before committing production capacity and equipment reservations tied to the auction.
  • Groups with renewable generation and batteries: assess the net effect of the charge on the portfolio, since the factors under discussion range from 25% to 100% depending on the flexibility of the source.
  • All agents: monitor Aneel's regulation and bill PL 3,716/2026, which may redefine the economic basis of the contracts.

Original source: MegaWhat — Abeeólica questiona rateio do encargo e judicializa leilões de baterias

Deploying battery energy storage (BESS) in Northeast Brazil for LRCAP 2026?

Request a site delivery assessment for your project. We sign an NDA before receiving any sensitive information.

Request the assessment

More energy storage news

Newsletter

Radar ENLACE, every Monday in your inbox

The week's news on energy storage and BESS in Brazil (regulator, planners, grid operator and industry), summarized in English with the practical takeaway. Free.

We send an email to confirm. Unsubscribe anytime with one click. Privacy