LRCap 2026: Aneel reverses EPP's 1.7 GW disqualification

In a 3-2 vote, Aneel reinstates the qualification of EPP's ION consortia in LRCap 2026 but requires proof of funds deposited within 15 calendar days.

On Tuesday, November 17, 2026, the board of the Brazilian Electricity Regulatory Agency (Aneel) voted three to two to restore the qualification of the six ION consortia, led by Evolution Power Partners (EPP), which won nearly 1.7 GW in thermal power plants in the 2026 capacity reserve auction (LRCap). The win, however, came with a condition. The consortia will have to demonstrate, within a short deadline, that the funds used to build up the equity of the consortium member companies were actually received in cash. The case concerns thermal plants, but the criteria applied matter to any developer planning to compete in capacity auctions, including with battery storage projects.

How the vote went

The vote of the rapporteur, director Gentil Nogueira, prevailed, joined by director-general Sandoval Feitosa and director Willamy Frota. Directors Ludimila Lima and Agnes da Costa were outvoted, aligned with the position of the Federal Attorney's Office at Aneel. Both the Attorney's Office and the Permanent Auction Committee (CPL) had argued for upholding the disqualification, on the grounds that the consortia had not sufficiently proven the economic and financial requirements set out in the tender notice.

With the appeal upheld, the agency lifted the disqualification of the ION I, ION II, ION III a, ION III b, ION IV and ION V consortia, partially ratified the auction result and awarded the projects to the winners. For those waiting in line, the immediate effect is the postponement of any call-up. Eneva and Global Participações em Energia were awaiting the outcome of the appeal, and Eneva was already preparing for a possible call-up of two plants, Porto Norte Fluminense I A and GDE Pará III, which together total about 791 MW of availability.

The condition imposed on the consortia

The qualification stands only if credits that consortium members EPP, Brazilian Energy Participações (BEP) and OAK Participações included in their equity, and that the CPL did not accept, are settled. The list includes:

  • promissory notes and receivables;
  • credits linked or not to Advances for Future Capital Increase (AFACs);
  • loans and dividends;
  • accounts and loans receivable.

The money must flow into the companies in an amount sufficient for each member's equity to reach the minimum required by the committee, excluding any credits that are not paid. Proof must be provided within 15 calendar days after publication of the ratification and award notice, with bank statements showing the inflow and origin of the funds. For AFACs, the corporate acts for the capitalization will also be required.

The rapporteur made two points clear. First, the deadline expires before promissory notes scheduled for December 30, 2026, which may require those payments to be brought forward, and the tender notice provides no basis for an extension. Second, settlement must be definitive: offsets or transactions in which the money returns, directly or indirectly, to whoever made the transfer will not count. If proof is not provided, the CPL must declare the disqualification, with due process and full right of defense guaranteed, which may lead to revocation of the award and the call-up of the remaining bidders.

The origin of the disagreement

The dispute arose when the CPL disregarded amounts recorded on the balance sheets of the consortium companies. The committee found that part of the credits had not been converted into cash and that cross-shareholdings among the members could result in double counting of equity. In other words, the debate was not about whether accounting entries existed, but whether they represented real financial capacity to back the commitment made in the auction.

What this means in the Northeast

Capacity auctions depend on two filters: having somewhere to connect and having the financial strength to fulfill the contract. On the first, the Northeast offers significant room. A survey by ENLACE based on the ONS technical note on connection margin identified 14 substations in Bahia, 10 in Ceará and 6 in Piauí with a margin of 500 MW or more among those eligible for LRCap 2026.

Aneel's decision is a reminder that a connection point is not enough. Battery developers in the region who intend to take up this margin in future auctions will need to reach qualification with their capital structure resolved, not just with the technical design and grid access well advanced.

Our take

In our assessment, the most important message lies not in the vote result but in the standard of proof it set. Even while ruling in favor of the consortia, Aneel demanded money actually deposited, with demonstrated origin and no flow back to the parties. We see here a trend toward a stricter reading of economic and financial qualification, which is likely to be adopted by those preparing bids for capacity auctions, including those that may cover storage.

The outcome remains open. The qualification is conditional and depends on a deadline that only begins to run upon publication of the ratification and award notice. If proof fails, the process returns to the CPL, with the right of defense, and the call-up of remaining bidders reemerges as a possibility. The split on the board, with opposing positions from the Attorney's Office and the committee itself, shows that the issue is not settled and may be debated again in future tender notices.

In the coming weeks, we will follow the publication of the notice, the delivery of statements and corporate acts within the 15 calendar days, any early payment of the promissory notes due on December 30, 2026 and, in the event of a new disqualification, the call-up of projects such as those of Eneva and Global.

What changes in practice for the BESS sector

Developers should plan the capitalization of special purpose companies and consortium members before qualification, avoiding reliance on receivables, intercompany loans or AFACs not yet effectively funded. Structures with cross-shareholdings deserve review to avoid double-counting challenges.

EPCs and battery manufacturers are likely to be sought more by partners with proven cash, and it is worth assessing clients' financial soundness before committing schedules and equipment reservations.

Suppliers and investors planning to join consortia as partners should formalize contributions in advance, with banking and corporate documentation ready. In auctions with short deadlines and no room for extensions, financial organization weighs as much as the technical quality of the project.

Original source: MegaWhat — EPP reverte inabilitação de 1,7 GW no LRCap, mas terá que comprovar recursos

Deploying battery energy storage (BESS) in Northeast Brazil for LRCAP 2026?

Request a site delivery assessment for your project. We sign an NDA before receiving any sensitive information.

Request the assessment

More energy storage news

Newsletter

Radar ENLACE, every Monday in your inbox

The week's news on energy storage and BESS in Brazil (regulator, planners, grid operator and industry), summarized in English with the practical takeaway. Free.

We send an email to confirm. Unsubscribe anytime with one click. Privacy