Battery auction to shape BYD's new factory decision in Manaus

BYD will wait for Brazil's capacity reserve auction for batteries before deciding on a Manaus factory, and sees Abeeólica's lawsuit as a source of uncertainty.

BYD will wait for the capacity reserve auction for batteries to take place before deciding whether to expand its industrial facilities in Manaus, Amazonas, or build a new factory in the city. The position was presented on November 17, 2026, by the company's vice president, Alexandre Baldy, in a conversation with journalists after the 2nd Sector Analysis Forum of the Electric Energy Trading Chamber (CCEE). On the same occasion, the executive pointed to the public civil action filed by the Brazilian Wind Energy Association (Abeeólica), which seeks to suspend the auctions, as a new source of uncertainty for those planning to invest in the sector.

Industrial decision tied to the auction

According to Baldy, the manufacturer is currently in talks with around 70 companies interested in buying battery energy storage systems, known as BESS. Even with this pipeline of negotiations, BYD treats the auction and local content requirements as decisive factors in defining the size and format of its industrial bet in Brazil. The choice between expanding existing capacity or building a new unit, according to the company, will depend on the contracting conditions and the demand outlook in the Brazilian market.

In June, the company had announced investments of up to R$ 500 million in batteries in the country, in a project linked to its industrial operation in Manaus and aimed at serving the domestic market. The unit is expected to reach a production capacity of up to 10 GW.

For those following the topic, it is worth recalling what is at stake. The capacity reserve auction is the mechanism through which the government contracts available power to ensure the security of the electricity system at times of higher demand. In the battery round, BESS projects compete to provide this availability, storing energy during periods of surplus and returning it when the grid needs it most. Contracts of this type provide revenue predictability and, consequently, signal to manufacturers the volume of equipment the country may demand.

Local content and BNDES accreditation

BYD had already criticized the initial minimum local content index of 15% required of storage systems seeking qualification in the auctions. In the company's view, the percentage is low. Local content rules set a minimum share of components or production stages made in the country, usually as a condition for access to financing or auctions. The higher the requirement, the greater the advantage tends to be for those who manufacture locally.

After its criticism, the manufacturer joined the list of companies accredited by the Brazilian Development Bank (BNDES) to take part in the auction. The accreditation places the company among the eligible suppliers under the financing rules linked to the auction.

Abeeólica's lawsuit and timeline expectations

Abeeólica's public civil action adds a judicial element to a process the market was already following closely. Baldy acknowledged the uncertainty brought by the dispute but said he does not expect the auction to be postponed, taking into account the re-election of President Luiz Inácio Lula da Silva.

The executive also addressed another front: the use of batteries from electric and plug-in hybrid vehicles as a resource for the electricity system. According to him, Brazil's fleet of these cars already totals almost 15 GWh of storage capacity. Baldy cited the company's actions during the floods in Rio Grande do Sul, when 50 vehicles were sent to supply electricity to Fire Department and Military Police facilities, and said that the batteries of 82 cars lost in the floods could be reused. He also mentioned the vehicle-to-grid (V2G) model, in which the vehicle owner charges the battery when energy is cheaper and returns electricity to the grid during the most expensive hours, stressing that the expansion of these applications depends on regulatory progress.

What this means for the Northeast

The factory's location matters for those developing projects in the region, because the route the batteries take to the construction site weighs on cost and schedule, whether the equipment is produced in the country or imported. According to ENLACE's survey of Northeastern substations eligible for the auction, the average distance to the nearest port is 202 km in Ceará, but reaches 624 km in Bahia and 707 km in Piauí. This means that at many inland connection points, overland transport of containers and transformers is a relevant planning stage, regardless of where the equipment comes from.

If domestic supply grows and local content rules gain weight, logistics between the production hub and the connection points will become part of the comparison between suppliers, alongside price, delivery time and warranties.

Our take

In our assessment, BYD's statement confirms something the battery market has been noticing: the local supply chain tends to form to the extent that there is firm contracting. A manufacturer that negotiates with dozens of buyers and still makes industrial expansion conditional on the auction shows that the auction works as a demand benchmark for the entire industry, not just for the winners.

We see two points still undefined. The first is the outcome of Abeeólica's public civil action: BYD's expectation that there will be no postponement is the company's assessment, not a guarantee, and any court decision could change the timeline. The second is the level of the local content requirement, already questioned by the manufacturer. Changes to this index would affect costs, supplier selection and financing structuring.

In the coming weeks, we recommend following the lawsuit's progress in court, the confirmation of the date and final rules of the auction, any revisions to the local content index and BYD's announcement on whether to expand or build a new unit in Manaus, which is expected after the auction.

What changes in practice for the BESS market

  • Developers: it is advisable to keep schedules with room for a possible judicial delay and to monitor whether domestic equipment supply materializes in time for projects.
  • EPCs: it is worth comparing scenarios with domestic and imported equipment, considering logistics to the substation and local content requirements.
  • Manufacturers: the auction tends to set the pace of industrial investment, and BNDES accreditation gains importance as a gateway.
  • Suppliers: the possible expansion in Manaus may open room for local components and services, but depends on contracting conditions that remain open.

Original source: MegaWhat — BYD condiciona nova fábrica de baterias em Manaus a leilão e vê risco em ação da Abeeólica

Deploying battery energy storage (BESS) in Northeast Brazil for LRCAP 2026?

Request a site delivery assessment for your project. We sign an NDA before receiving any sensitive information.

Request the assessment

More energy storage news

Newsletter

Radar ENLACE, every Monday in your inbox

The week's news on energy storage and BESS in Brazil (regulator, planners, grid operator and industry), summarized in English with the practical takeaway. Free.

We send an email to confirm. Unsubscribe anytime with one click. Privacy