On Wednesday, November 25, the Federal Court of the Federal District rejected the request for urgent injunctive relief filed by the Brazilian Association of Wind Energy and New Technologies (Abeeólica) to suspend the capacity reserve auctions aimed at contracting battery energy storage systems. The auctions, scheduled for December 2 and 4, will go ahead. The decision was issued by Judge Diego Câmara, of the 17th Federal Civil Court of the Federal District, in the public civil action the association filed on November 16 against the Federal Government and the National Electric Energy Agency (ANEEL).
What Abeeólica is challenging
The lawsuit targets two points. The first is the constitutionality of the rule that places the cost of contracting the batteries solely on generators. The second is holding the auctions before the final regulation on how this charge will be allocated is ready. In general terms, the capacity reserve auction (LRCAP) is the mechanism through which the system contracts resources capable of delivering power when demand is tight, and battery energy storage systems (BESS) come in precisely to provide this availability during critical hours. The cost of this reserve is recovered through a charge, and the dispute centers on who pays and how that amount is divided.
In addition to the first-instance lawsuit, the association also filed a direct action of unconstitutionality (ADI) with the Federal Supreme Court (STF), which is proceeding on its own track.
Grounds for the decision
The judge concluded that the requirements for granting urgent relief were not met. The main arguments were:
- Origin of the rule: assigning the cost to generators was an explicit choice of the Legislature, not a decision by ANEEL or the Ministry of Mines and Energy (MME).
- Limited effect of a possible unconstitutionality ruling: according to the judge, paragraph 6 only addresses who bears the charge. If it is struck down, what changes is the paying base, without affecting the validity of the auctions or of the contracts signed as a result of them.
- No imminent harm: charging generators only begins on August 1, 2028, which leaves time to finalize the allocation regulation, rule on the merits of the public civil action and review the ADI at the STF.
- Security of supply: suspending the auctions could jeopardize the electricity supply.
With the request denied, the case moves forward. The judge ordered the Federal Government and ANEEL to be summoned to present their defense, after which the Federal Public Prosecutor's Office (MPF) is to issue its opinion.
Charge allocation does not hold up the auctions
Another argument rejected was that the auctions would depend on first defining the methodology for splitting costs among generators. According to the decision, no legal or regulatory provision imposes this condition. ANEEL's regulation must be in place before the first settlement cycle of the supply period, not before the auction.
The agency itself noted in its filing that the first capacity reserve auction in the form of power, in December 2021, took place almost three years before the normative resolution that governed the allocation of that charge. In other words, there is precedent for contracting ahead of the charging rule.
On the proposal to differentiate the charge according to the flexibility of each source, a point contested by Abeeólica, the judge noted that there is still no final methodology approved by ANEEL's board. The decision also records that the agency is evaluating an alternative proposal from the National Electric System Operator (ONS). In the judge's view, if the normative act eventually issued contains any illegality, it can be challenged in court before any charge is applied, with no need to halt the contracting process.
What this means for the Northeast
With the auctions confirmed, competition for connection points returns to the center of planning. According to an ENLACE survey of Northeastern substations eligible for the auction, cross-referenced with the ONS technical note on connection margin, Bahia has 14 substations with a margin of 500 MW or more, Ceará has 10 in that range and Piauí has 6. These are points where larger projects have more room to connect.
For developers in the region, the decision reduces uncertainty about the auction date and reinforces the importance of having substation selection and connection documentation well sorted out, since competition tends to concentrate where margin is available.
Our take
In our assessment, the decision signals that the Judiciary tends to separate the debate over who pays the charge from the contracting itself. By stating that a possible unconstitutionality would only change the paying base, the judge preserves the contracts that will come out of the auctions, which is relevant to the bankability of storage projects. We see this as an element of predictability for a market that is still taking its first steps in the country.
This does not settle the matter. It is a preliminary decision, and the merits of the public civil action have yet to be ruled on, as does the ADI at the STF. The allocation methodology also remains open, with the proposal to differentiate by source flexibility and the alternative submitted by the ONS still under review at ANEEL. The discussion over cost recovery may continue to generate industry debate and possibly new legal actions, even though the judge himself pointed out that review can take place before any charge is applied.
In the coming weeks, we will follow the auctions on December 2 and 4, the defenses of the Federal Government and ANEEL, the MPF's opinion and the progress of the allocation regulation, which must be operational before the first settlement cycle, with charging scheduled to start on August 1, 2028.
What changes in practice for the BESS sector
- Developers: can continue preparing for the December 2 and 4 auctions, with lower risk of annulment of any contracts signed.
- EPCs: the confirmed schedule makes it possible to plan teams and deployment timelines based on the dates already set.
- Manufacturers and suppliers: keeping the auctions on track preserves expected demand and justifies continuing ongoing supply negotiations.
- All players: it is worth monitoring the allocation regulation at ANEEL and the progress of the lawsuits, which may affect how the charge is distributed among generators, though not the validity of the contracts, according to the judge's understanding.
Original source: MegaWhat — Justiça nega pedido da Abeeólica para suspender leilões de baterias