On Tuesday, November 17, 2026, the board of the Brazilian Electricity Regulatory Agency (Aneel) once again postponed its decision on TermoG's appeal against its disqualification from the 2026 capacity reserve auction (LRCap). Director Willamy Frota requested a review of the case right after director Gentil Nogueira presented a review vote in favor of upholding the disqualification, in line with the vote cast in August by then-director Fernando Mosna. As a result, the case remains unresolved, and the debate over how to prove economic and financial capacity in capacity auctions gains another chapter.
What is at stake in TermoG's appeal
The case involves the qualification of UTE Garuva, a thermal power plant that submitted a bid of R$ 2.735 million/MW.year in the product with supply starting in 2028. The Permanent Auction Committee (CPL) disqualified the company, and TermoG appealed, asking to be recognized as a Special Purpose Company (SPE). This classification would allow it to use the net worth of its direct parent company, Mar Engenharia e Produção de Gás e Energia, to meet the economic and financial capacity requirement set out in the auction notice.
Broadly speaking, power sector auction notices require bidders to demonstrate financial size compatible with the project they intend to build. When the project is structured in a newly created SPE, it is common to rely on the controlling company's balance sheet to meet this requirement. The question, in TermoG's case, is which assets can actually be attributed to that parent company.
The numbers that weighed against the company
In his August vote, Mosna acknowledged that TermoG could be treated as an SPE, but concluded that the direct parent company did not have sufficient net worth. At the heart of the dispute are R$ 65 million in real estate registered in the name of Tirreno Brava Residenziale Construtora e Incorporadora SPE, another company in the same economic group. According to the CPL, without these assets Mar Engenharia's net worth would be R$ 2.86 million, well below the required minimum of R$ 30.16 million.
In siding with the original rapporteur, Gentil Nogueira emphasized the principle of the asset autonomy of legal entities. In the director's view, the existence of corporate ties between companies in a group does not authorize the automatic transfer of assets from one to another when proving qualification requirements. Therefore, it would not be legally acceptable to count as belonging to Mar Engenharia assets that formally belong to another company.
The difference from the ION consortia
Gentil Nogueira also made a point of distinguishing TermoG's case from the appeal of the ION consortia, led by Evolution Power Partners (EPP), which had prompted his request for review in August. In TermoG's case, the properties are registered to a company that did not take part in the auction. In the consortia's case, the debate concerned the treatment of assets recorded on the participants' own balance sheets. At the same session, Aneel overturned by majority the disqualification of the six ION consortia, which together total nearly 1.7 GW in thermal plants, but on the condition that they prove their funds.
Gentil's vote also endorsed the instruction for the CPL to take the necessary steps to call and qualify other bidders that submitted valid bids in the auction. This part, however, depends on the conclusion of the ruling, which was suspended by Willamy Frota's request for review.
What this means in the Northeast
The dispute concerns qualification, but the ultimate effect of a disqualification is to open room for other bids and, in future auctions, to influence who is able to compete for the available connection points. According to an ENLACE survey of substations eligible for LRCap 2026 in the Northeast, Bahia has 14 substations with a connection margin of 500 MW or more, Ceará has 10, and Piauí has 6. In other words, there is significant grid capacity in the region, and those who intend to compete for it with battery projects need to reach the qualification stage with financial documentation free of weak points.
An available connection margin only becomes a contract if the bidder clears every stage of the auction. Losing qualification over a corporate or accounting issue means leaving the connection point to another competitor, even with a technically well-positioned project.
Our take
In our assessment, the votes already cast in TermoG's case point to a clear line: the net worth used for qualification must be on the balance sheet of the auction participant or its direct parent company, not spread across other group companies. For the storage market, this reinforces something we see frequently: the corporate structure of a BESS project must be designed for qualification from the outset, not adjusted on the eve of the auction.
Some points remain undefined. Willamy Frota's request for review prevents, for now, a majority from forming, and we do not know whether the next vote will follow the same line or bring a different interpretation. It is also unclear how the CPL will handle calling other bidders if the disqualification is confirmed, and how the proof of funds required from the ION consortia will be verified in practice.
In the coming weeks, it is worth following the case's return to the Aneel board agenda, Willamy Frota's vote, and any steps taken by the CPL. These developments should consolidate the agency's understanding of economic and financial capacity in capacity auctions.
What changes in practice for BESS players
- Developers: concentrate the required net worth in the SPE or the direct parent company, avoiding reliance on assets registered to other group companies.
- EPCs: expect more due diligence from clients on schedule and financial strength, since disqualifications can change the list of contracted projects.
- Manufacturers and suppliers: assess the corporate and financial robustness of partners before reserving equipment or signing supply agreements tied to the auction result.
- All market players: follow Aneel's decisions on LRCap 2026 appeals, which serve as a reference for preparing future auctions.