Brazil's Ministry of Development, Industry, Trade and Services (MDIC) submitted to the National Electric Energy Agency (ANEEL), on November 23, its contribution to public consultation No. 037/2026. The consultation addresses how to split the costs of the capacity reserve auction in the form of energy storage (LRCAP-SAE). The ministry supports including all generators in the cost sharing, with discounts according to the flexibility each plant provides to the National Interconnected System (SIN). At the same time, it argues that Congress should repeal the provision of Law 15.269 that assigns payment for the batteries solely to generators. The submission comes just days before the auctions scheduled for December 2 and 4.
How flexibility-based cost sharing would work
The capacity reserve auction (LRCAP) contracts power availability to provide security to the system at times of higher demand. In this round, the product is battery energy storage systems (BESS), which can absorb energy during hours of surplus and return it when the grid needs it most. The revenue of these projects is paid through a charge, and ANEEL's consultation discusses precisely who bears it.
MDIC followed the agency's technical assessment and chose alternative 3, based on the Flexibility Index (IF). Under this design, all generators remain in the funding base, but pay different shares of the unit charge:
- P1 (inflexible): 100% of the charge;
- P2 (low flexibility): 75%;
- P3 (high flexibility): 50%;
- P4 (very high flexibility): 25%.
In ANEEL's multi-criteria analysis cited by the ministry, this option scored 4.41 points. It ranked ahead of the alternative that would charge only non-flexible generators, with 3.37 points, and of uniform sharing among all generators, with 3.01 points.
Regulatory support, but criticism of the law
The ministry makes clear that choosing the best option within the current rule does not mean agreeing with it. In its view, the most appropriate path for supply security and for consumers and self-producers would be to repeal the legal provision that concentrates funding on generators. Until the law changes, MDIC supports differentiating the charge by flexibility.
The document argues that generators should not be held responsible for the expansion of intermittent sources, such as wind and solar, contracted in auctions or encouraged in the Free Contracting Environment (ACL). It also mentions the effects of curtailment, that is, generation cuts ordered by system operation, and losses of R$ 6.5 billion for wind generators in 2025.
The technical note goes beyond batteries. It calls for ending discounts on transmission and distribution system usage tariffs (TUST and TUSD) for renewables, a cap on subsidies for distributed micro- and minigeneration, in line with PLP No. 100/2026, and the gradual reduction of these benefits for units covered by Article 26 of Law No. 14.300/2022. It also proposes more accurate price signals in the short-term market, a stronger locational signal in transmission and time-of-use tariffs for low voltage.
A charge contested on several fronts
The generator-only funding rule is also being challenged outside ANEEL. On November 19, the Brazilian Wind Energy Association (Abeeólica) took the issue to the Federal Supreme Court (STF). In the Chamber of Deputies, Bill No. 3.716/2026 is moving under urgency procedures to remove this exclusive obligation from generators.
The debate over the economic impact is also open. The National Front of Energy Consumers (FNCE) estimates that the bill could raise energy expenses by up to R$ 6.26 billion per year, or R$ 94 billion over 15 years, in a scenario of 5 GW contracted. The Brazilian Association of Energy Storage Solutions (ABSAE) disputes this calculation. According to the association, 4.5 GW of batteries could generate benefits of up to R$ 5.5 billion per year, about 90% of them for consumers, considering lower capacity costs, system service charges and spilled energy.
What this means for the Northeast
The Northeast hosts a large share of the country's wind and solar generation, so the way the charge is divided carries significant weight for plants in the region. For BESS developers, the funding dispute adds to another well-known variable: connection availability. According to a survey by ENLACE, 27 substations in Bahia, 24 in Ceará and 15 in Piauí eligible for LRCAP 2026 appear with connection margin in the ONS technical note.
This set of connection points remains the basis for those competing in the December auctions. The definition of who pays the contracted revenue, however, affects the perceived risk of these projects, including in the region.
Our take
In our assessment, MDIC's position indicates that the government recognizes the value of batteries for the system and is seeking a less contested payment formula. Tiering by the Flexibility Index creates a coherent signal: those who contribute more to operations pay less. We see this as progress compared with a uniform charge or one restricted to a few agents.
The point of attention is that the payment base may still change through three parallel paths: ANEEL's decision on the public consultation, the STF case and Bill 3.716/2026. None has a known outcome, and a change after the auctions could reopen discussions on cost allocation. We also believe that the FNCE and ABSAE estimates, very far apart, show that the debate on costs and benefits for consumers is far from over.
In the coming weeks, we will follow the auctions on December 2 and 4, ANEEL's deliberation on consultation No. 037/2026, the bill's progress in the Chamber and any STF decisions.
What changes in practice for the BESS chain
- Developers: should factor into bids and risk analyses the possibility of changes in the base of charge payers, and follow ANEEL's final regulations.
- EPCs: should provide in contracts for how any regulatory changes that alter project schedules or financing conditions will be handled.
- Manufacturers and suppliers: demand depends on the auction results, but the legal certainty of the charge is likely to influence the pace of order closings.
- All links: MDIC's broader agenda, with time-of-use tariffs and more accurate price signals, may in the future expand storage revenue opportunities beyond capacity reserve.
Original source: MegaWhat — MDIC defende fim da cobrança exclusiva de geradores por baterias