Petrobras released its 2027-2031 Business Plan on the evening of Monday, November 23, and for the first time the document makes room for battery energy storage systems (BESS). The state-owned company intends to develop these projects alone or with partners, focusing on capacity reserve auctions (LRCap). The same plan allocates US$ 600 million to new thermal power plants and cuts the budget for solar photovoltaic and onshore wind generation by 54%. For the storage market, the core message is that one of the country's largest companies will now compete, directly or indirectly, for the space opened by the battery auction scheduled for December.
Batteries on the state-owned company's radar
According to the plan, Petrobras's main entry point into storage will be the LRCaps, auctions in which the power system contracts available capacity for moments of greatest need, remunerating capacity and not just the energy delivered. It is a format well suited to batteries, which can respond within seconds and shift energy throughout the day.
The most concrete vehicle for this strategy is Lightsource BP, in which Petrobras acquired a 49.99% stake in December 2025. According to the company, the joint venture registered projects of "relevant capacity" in the battery LRCap scheduled for December this year. Through this partnership, Petrobras also holds a portfolio of between 1 GW and 1.5 GW at a more advanced stage of development, although it acknowledges that some projects were abandoned or faced grid connection difficulties.
Its interest goes beyond the auctions. The company is evaluating research, development and innovation initiatives in critical minerals, prioritizing those with the most synergy with its businesses, and explicitly mentions the battery value chain, from prospecting and extraction to refining and pack assembly. The plan also points to the electrification of traditional sectors and new demand, such as data centers and electric mobility, as drivers of electricity consumption growth, in addition to expanding sales in the free market and decarbonizing its own operations, in line with its goal of net-zero operational emissions by 2050.
Thermal plants get a boost
Alongside batteries, Petrobras is doubling down on thermal generation. The highlight of the planned US$ 600 million is the plants at the Boaventura Energy Complex, formerly Comperj, in Rio de Janeiro, with a projected capacity of 800 MW.
The company had already expanded its presence in this segment in this year's March LRCap, when it won with gas and diesel projects. As a result, the contracted capacity of its thermal fleet rose from 2 GW to 4.6 GW, with total fixed revenue of R$ 65 billion. When dispatched, the gas plants can consume up to 16.6 million cubic meters per day, with fuel remunerated separately through the Unit Variable Cost (CVU).
Less money for solar and wind
On the other hand, the budget for onshore wind and solar fell 53.8% compared to the previous plan, from US$ 1.73 billion in the 2026-2030 BP to US$ 800 million. The total low-carbon portfolio also shrank 17.2%, from US$ 6.4 billion to US$ 5.3 billion. On the same day as the plan, the company announced the purchase of 42% of Neomille, a corn ethanol producer from the CerradinhoBio group, for R$ 2.8 billion. On the 12th of this month, it had already taken full control of Logum Logística by acquiring the 70% it did not yet own for R$ 620 million.
What this means for the Northeast
The source does not detail where the projects registered by Lightsource BP are located, but the mention of connection difficulties touches on an issue we know well in the region. According to ENLACE's survey, among the Northeastern substations eligible for the LRCap, 27 in Bahia, 24 in Ceará and 15 in Piauí appear in the ONS technical note with connection margin. This indicates there is physical room on the grid for battery projects in these states, but also that competition for these points is likely to intensify as large players enter the game.
For developers in Ceará, Piauí and Bahia, connection margin remains the decisive filter: well-positioned projects on the grid gain value both for competing and for negotiating partnerships with investors seeking auction-ready assets.
Our take
In our assessment, the inclusion of batteries in Petrobras's plan is a sign of maturity for the Brazilian storage market. When a company of this size starts treating BESS as a business line rather than an experiment, the sector gains a benchmark for financiers, suppliers and planning bodies. We also see strategic coherence: the company combines thermal plants and batteries precisely in the capacity product, while reducing its exposure to pure renewable generation.
There are, however, open questions. The plan does not report specific amounts for storage, nor how many megawatts Lightsource BP registered, since the description is limited to "relevant capacity". The acknowledgment of withdrawals and connection difficulties itself shows that not every registered project reaches the bidding or contract stage. It is also unclear whether the company intends to act mainly as a direct investor or through partnerships.
In the coming weeks, we will follow the December battery LRCap, the result obtained by Lightsource BP and any Petrobras partnership announcements in storage. Developments on the critical minerals and pack assembly front deserve attention in the medium term, as they may influence the domestic supply chain.
What changes in practice for the BESS sector
- Developers: Petrobras's arrival may mean stronger competition in the auction, but also a potential buyer or partner for projects with well-resolved connection and advanced permitting.
- EPCs: a large-scale portfolio, if it moves forward after the auction, is likely to require execution capacity at scale and strict governance standards, favoring companies prepared for demanding qualification processes.
- Manufacturers: the mention of pack assembly and critical minerals suggests interest in a local supply chain; it is worth watching how this translates into procurement requirements.
- Service providers: connection studies, owner's engineering and risk management gain relevance, since the company itself admits grid access obstacles in some of its projects.
In short, the December auction now has another heavyweight participant, and the technical preparation of projects becomes even more decisive for those who want to compete or partner.
Original source: MegaWhat — Petrobras inclui baterias e US$ 600 milhões para novas térmicas no planejamento