Transportadora Brasileira Gasoduto Bolívia-Brasil (TBG) sent a letter to the National Agency of Petroleum, Natural Gas and Biofuels (ANP) on Tuesday, November 17, 2026, warning that the pipeline investments needed to deliver gas to the thermal plants that won the Capacity Reserve Auction in the form of Power (LRCap), held in March, were given no regulatory treatment at all in the transmission companies' tariff review. The next day, ANP resumed the process and opened a public consultation with a shortened deadline. The episode exposes a weak point in the chain that is supposed to guarantee the power contracted in the auction.
What TBG is challenging
At the heart of the complaint is Board Decision No. 733/2026, which set the regulatory asset base (BRA) of the transmission companies for the 2026-2030 cycle and classified the planned investments, approving some of them and imposing reservations on others. According to TBG, the works tied to serving the LRCap plants did not fall into any of the categories, not even that of conditionally approved capex.
The difference matters. In the case of conditional capex, the agency has already assessed the merits and only proof of execution is pending. For the LRCap investments, the company says there is no definition of whether they will be recognized, when, through what procedure and at what value, whether in the BRA, in the Maximum Allowed Revenue (RMP) or in tariffs. In the company's view, this would force it to build infrastructure for long-term commitments of the power sector without knowing how it would recover the capital, a situation it describes as seriously harmful to legal certainty and predictability.
For this reason, TBG asks that the 3rd phase of the tariff review explicitly address these investments, with criteria and an approval procedure, including for cases where construction authorization is granted mid-cycle, and with rules for the subsequent inclusion of the amounts in the BRA, the RMP and tariffs.
The scale of the works and pending capex
Earlier reports by the same outlet indicate the size of what is at stake. TBG expects to spend around US$ 300 million to serve the auction's thermal plants and has signed contracts with winning plants based on liquefied natural gas arriving through the Terminal Gás Sul. The company has also asked ANP to authorize a US$ 286 million project that expands Gasbol's capacity and connects the J&F terminal in Santa Catarina, considered necessary for the new thermal power demand.
In addition, the letter cites R$ 786.4 million, at December 2025 prices, classified as conditionally approved. TBG states that neither the conditions for submitting the information required by the agency nor the deadlines for these amounts to reach tariffs have been defined, and attributes the gap to regulatory omission, not to the law. According to the company, this is not expansion but recurring spending on integrity, operational safety and service continuity in a mature asset. The company argues that shippers need to know whether and when these amounts will be incorporated, otherwise contracting capacity will become more difficult.
ANP's timeline
ANP reopened the tariff review on November 18 and put the matter to public consultation. To conclude the process still in 2026, the agency cut the comment period from 15 to ten days and waived the public hearing. The short window means that any response to TBG's request, if it comes, should appear in the final deliberation of the 3rd phase, with few intermediate opportunities for adjustment.
What this means for the Northeast
The letter concerns pipelines along the Gasbol corridor, not Northeastern projects, but the logic of the LRCap is national: the auction contracts available power, and any delay in one source reinforces the importance of technologies that depend less on external infrastructure. For batteries, the main bottleneck is usually the grid connection, not fuel supply. According to a survey by ENLACE, in Ceará 24 eligible substations appear in the ONS technical note with connection margin; in Bahia, 14 have a margin of 500 MW or more; and in Piauí, 6 reach that level.
These figures do not guarantee winning an auction, but they show there is physical room on the region's grid for well-structured storage projects, without dependence on pipelines, LNG terminals or gas transportation contracts.
Our take
In our assessment, the news illustrates a risk that goes beyond TBG: the thermal power contracted in the LRCap depends on a chain of investments in another regulated sector, with another agency and another timeline. When the remuneration for these works remains undefined, the chance grows that the promised availability arrives later or at a higher cost. We see this as an argument for diversifying the capacity reserve with batteries, which have shorter deployment times and a supply chain more concentrated within the project itself.
Much remains open. ANP may accept the request and create a clear procedure, which would reduce uncertainty for the thermal plants; it may also handle the issue in a separate process. The letter does not allow the conclusion that the plants will be delayed, and power sector planning can respond in various ways. Batteries also face their own regulatory risks, such as remuneration rules and grid access.
In the coming weeks, we will follow the contributions to the ten-day public consultation, the text of the final deliberation of the 3rd phase of the tariff review, the decision on the authorization request for the Gasbol expansion project and the fate of the R$ 786.4 million under conditional approval.
What changes in practice for BESS players
- Developers: it is worth reinforcing, in discussions with sector planners, the timing advantage and logistical independence of batteries in supplying power.
- EPCs: the ability to deliver on schedule becomes an even more visible differentiator compared with sources that depend on third-party works.
- Manufacturers and suppliers: it is prudent to keep production and logistics planning aligned with possible new capacity auctions, without anticipating demand that has not yet been defined.
- Everyone: following the gas tariff review helps to understand the cost and risk of the alternatives storage competes with.