Battery auction: WEG accredited under BNDES route 2

BNDES accredits WEG's lithium battery pack under route 2, unlocking up to 100% Fundo Clima financing for the LRCap auction starting December 2.

WEG has received accreditation from the Brazilian Development Bank (BNDES) for its lithium battery pack under the so-called route 2 for local content. With the registration, announced on November 25, 2026, the manufacturer is now eligible to supply equipment for the country's first capacity reserve auction (LRCap) focused on storage systems, which begins on Wednesday, December 2. Moura had already secured the same approval, putting two domestic suppliers accredited under the same route on the eve of the auction.

What route 2 is and why it matters for financing

BNDES organizes local content requirements for battery energy storage systems (BESS) into different paths, known as routes. Broadly speaking, local content is the share of the equipment produced or processed in Brazil, and this criterion is what grants access to the bank's credit lines with preferential terms.

Route 2 differs from other modalities because it does not allow the local content requirement to be met with accessory components alone. It focuses on production stages of the battery system itself, precisely the item that accounts for much of the value of a BESS. In practice, it is a more demanding criterion for the manufacturer, but one that delivers a significant benefit to the buyer.

That benefit lies in the cost of capital. Routes 2, 3 and 4 allow financing of up to 100% of the equipment value with Fundo Clima resources, at a nominal cost of 6.5% per year. For capital-intensive projects that rely on long-term contracts, such as those to be contracted in the LRCap, access to cheap credit can make a direct difference in bid competitiveness.

WEG, Moura and the bet on domestic manufacturing

In Moura's case, accreditation was obtained under route 2 of the CFI-Finame sector regulation, for a BESS that will use technology from China's CATL. WEG, in turn, presents its qualification as part of a strategy that goes beyond regulatory compliance and cell-level localization. According to Harry Schmelzer Neto, the company's Sales Director for Solar, BESS and Building, the aim is to help build a Brazilian storage industry with greater technological content and autonomy, supporting system stability and the use of renewable sources.

To support this strategy, WEG will build a new factory at its Itajaí complex, in Santa Catarina:

  • Capacity: 4 GWh per year;
  • Investment: R$ 330 million, through the BNDES Mais Inovação program;
  • Start of operations: expected in the second half of 2027.

The auction context

The accreditation comes at a busy time. Two capacity reserve auctions for batteries are scheduled, on December 2 and 4, and Aneel extended online registration until November 23. On the same November 25, the Federal Court of the Federal District denied Abeeólica's request for an injunction to suspend the auctions. The association also filed a lawsuit with the STF on November 19 against charging battery costs exclusively to generators.

The debate over who pays remains open. MDIC argued that all generators should share the costs, with discounts proportional to each plant's flexibility. Absae estimates benefits of up to R$ 5.5 billion per year for consumers from batteries, while FNCE calculates that bill PL 3.716/2026 could raise electricity bills by up to R$ 6.26 billion annually by shifting these costs to all consumers. Meanwhile, BNDES signaled that it may finance up to 80% of the total investment of LRCap projects with local content, with flexibility in amortization and guarantees.

What this means for the Northeast

For those planning to compete in the LRCap in the Northeast, having accredited domestic suppliers broadens financial structuring options, but the starting point remains the grid connection. An ENLACE survey of substations eligible for LRCAP 2026 indicates that 27 substations in Bahia, 24 in Ceará and all 15 analyzed in Piauí appear in the ONS technical note with connection margin.

This means there is physical room on the grid for projects in the region, and that the choice between domestic equipment financed by Fundo Clima and imported alternatives becomes one more variable in modeling each connection point, not a substitute for grid analysis.

Our take

In our assessment, the accreditation of WEG and Moura under route 2 signals that local content policy is beginning to see concrete supply on the industrial side. For developers, this turns financing at 6.5% per year with up to 100% Fundo Clima coverage into a real, not merely theoretical, option when building bids.

At the same time, we see points still undefined. WEG's new factory is only expected to operate in the second half of 2027, which calls for attention to the delivery schedule against commitments made in the auction. The legal and regulatory dispute over cost sharing, with a lawsuit at the STF and a bill under consideration, may also influence investors' risk perception, even with the injunction denied.

In the coming weeks, we will follow the results of the December 2 and 4 auctions, the participation of accredited equipment in winning projects, any new accreditations under BNDES routes, and the progress of Abeeólica's lawsuit and PL 3.716/2026.

What changes in practice for the BESS market

  • Developers: will compare, on the same spreadsheet, the cost of domestic equipment with Fundo Clima credit against imported solutions with other financing sources.
  • EPCs: need to prepare to integrate systems from domestic manufacturers and align delivery times with contract schedules.
  • Manufacturers: the route 2 benchmark, centered on the battery system itself, tends to guide productive investment decisions in the country.
  • Suppliers: demand for local production stages may open room for the BESS-related component and service chain.

Original source: MegaWhat — WEG habilita sistema de baterias para leilão de reserva de capacidade

Deploying battery energy storage (BESS) in Northeast Brazil for LRCAP 2026?

Request a site delivery assessment for your project. We sign an NDA before receiving any sensitive information.

Request the assessment

More energy storage news

Newsletter

Radar ENLACE, every Monday in your inbox

The week's news on energy storage and BESS in Brazil (regulator, planners, grid operator and industry), summarized in English with the practical takeaway. Free.

We send an email to confirm. Unsubscribe anytime with one click. Privacy